please tell the answer asap with explanation or you can send your solutions pic
Attachments:
Answers
Answered by
2
Answer:
0.8 = 80% of the project
Step-by-step explanation:
Amount of the project completed in 10 days = 10/10 = Full project
Amount of the project completed in 1 day = 1/10 = 10% of the project
Amount of the project completed in 8 days = 1/10 x 8 = 8/10 = 80% of the project
Therefore, the amount of the project completed in 8 days = 80%