Answer:
24 days
1st answer
is 24 days
Answered by
1
1.(3.)
60 x 2/5 = 24 days
2. A in 1 day = 1/15 part of work
B in 1 day = 1/10 part of work
A and B together can finish 1/10 + 1/15 = 5/30 = 1/6 part of work in 1 day
So, altogether they can finish it in 6 days
60 x 2/5 = 24 days
2. A in 1 day = 1/15 part of work
B in 1 day = 1/10 part of work
A and B together can finish 1/10 + 1/15 = 5/30 = 1/6 part of work in 1 day
So, altogether they can finish it in 6 days