Math, asked by raopritesh2011, 4 months ago

pls ans question of work and time pls ans correctly​

Attachments:

Answers

Answered by george0096
4

Step-by-step explanation:

10)

A's one day work = 1/10

B's one day work = 1/12

C's one day work = 1/15

(A + B + C)'s one day work:

\dfrac{1}{10}+\dfrac{1}{12}+\dfrac{1}{15}

=\dfrac{6+5+4}{60}

=\dfrac{15}{60}

=\dfrac{1}{4}

Work left after A leaves:

1-\dfrac{1}{4}

=\dfrac{4-1}{4}

=\dfrac{3}{4}

(B + C)'s one day work:

\dfrac{1}{12}+\dfrac{1}{15}

=\dfrac{5+4}{60}

=\dfrac{9}{60}

=\dfrac{3}{20}

Work left after B leaves:

\dfrac{3}{4}-\dfrac{3}{20}

=\dfrac{15-3}{20}

=\dfrac{12}{20}

=\dfrac{3}{5}

As, C does 1/15 work in one day.

Therefore,

\sf{C\: can \: complete\:\dfrac{3}{5}\: work\: in:}

\dfrac{3}{5}\div\dfrac{1}{15}

\dfrac{3}{5}\times15

\dfrac{3}{1}\times3

\dfrac{9}{1}

9

Hence, C can complete the remaining work in \sf{9} days.

-------------------------

11)

A's one day work = 1/10

B's one day work = 1/15

(A + B)'s two day work if they work alternatively:

\dfrac{1}{10}+\dfrac{1}{15}

=\dfrac{3+2}{30}

=\dfrac{5}{30}

=\dfrac{1}{6}

Time taken to complete the work:

1\div\dfrac{1}{6}

=1\times6

=6

Because we calculated (A + B)'s two day work.

Therefore we will multiply the result by 2.

Multiplying the result by 2:

6 × 2

= 12

Hence, the work will be completed in 12 days.

-------------------------

12)

Let us assume:

  • B can complete the work in 2x days.

Then,

  • A can complete the work in x days.

Hence,

  • A's one day work = 1/x
  • B's one day work = 1/2x

Because,

(A + B) can complete the work in 14 days.

Therefore,

(A + B)'s one day work = 1/14

Transposing the values,

\dfrac{1}{x}+\dfrac{1}{2x}=\dfrac{1}{14}

\dfrac{2+1}{2x}=\dfrac{1}{14}

\dfrac{3}{2x}=\dfrac{1}{14}

By cross multiplication:

2x = 3 × 14

2x = 42

x = 21/2

x = 21

Hence, x = 21

Therefore, A can complete the work in 21 days.

-------------------------

13)

Let us assume:

  • B can complete the work in 3x days.

Then,

  • A can complete the work in x days.

Hence,

  • A's one day work = 1/x
  • B's one day work = 1/3x

Because,

(A + B) can complete the work in 15 days.

Therefore,

(A + B)'s one day work = 1/15

Transposing the values,

\dfrac{1}{x}+\dfrac{1}{3x}=\dfrac{1}{15}

\dfrac{3+1}{3x}=\dfrac{1}{15}

\dfrac{4}{3x}=\dfrac{1}{15}

By cross multiplication:

3x = 4 × 15

3x = 60

x = 60/3

x = 20

Hence, x = 20

Therefore, A can complete the work in 20 days.

-------------------------

14)

12 men can do a work in 8 days.

1 man can do the work in (8 × 12) days.

= 96 days [less men, more days]

16 men can do the work in (96/16) days.

= 6 days [more men, less days]

Similar questions