pls ans question of work and time pls ans correctly
Answers
Step-by-step explanation:
10)
A's one day work = 1/10
B's one day work = 1/12
C's one day work = 1/15
(A + B + C)'s one day work:
Work left after A leaves:
(B + C)'s one day work:
Work left after B leaves:
As, C does 1/15 work in one day.
Therefore,
Hence, C can complete the remaining work in days.
-------------------------
11)
A's one day work = 1/10
B's one day work = 1/15
(A + B)'s two day work if they work alternatively:
Time taken to complete the work:
Because we calculated (A + B)'s two day work.
Therefore we will multiply the result by 2.
Multiplying the result by 2:
6 × 2
= 12
Hence, the work will be completed in 12 days.
-------------------------
12)
Let us assume:
- B can complete the work in 2x days.
Then,
- A can complete the work in x days.
Hence,
- A's one day work = 1/x
- B's one day work = 1/2x
Because,
(A + B) can complete the work in 14 days.
Therefore,
(A + B)'s one day work = 1/14
Transposing the values,
By cross multiplication:
2x = 3 × 14
2x = 42
x = 21/2
x = 21
Hence, x = 21
Therefore, A can complete the work in 21 days.
-------------------------
13)
Let us assume:
- B can complete the work in 3x days.
Then,
- A can complete the work in x days.
Hence,
- A's one day work = 1/x
- B's one day work = 1/3x
Because,
(A + B) can complete the work in 15 days.
Therefore,
(A + B)'s one day work = 1/15
Transposing the values,
By cross multiplication:
3x = 4 × 15
3x = 60
x = 60/3
x = 20
Hence, x = 20
Therefore, A can complete the work in 20 days.
-------------------------
14)
12 men can do a work in 8 days.
1 man can do the work in (8 × 12) days.
= 96 days [less men, more days]
16 men can do the work in (96/16) days.
= 6 days [more men, less days]