(A+B+C) work in one day = 1/5
(A+C) work in one day = 1/15/2= 2/15
B's work in one day = (A+B+C) work in one day - (A+C) work in one day
= 1/5 - 2/15
=(3-2) / 15
= 1/15
So B can do 1/15 work in one day
so B can complete the work alone in 15 days.
A's work in one day = 1/15
C's work in one day = (A+C) work in one day - A's work in one day
= 2/15 - 1/15
= 1/15
(B+C) work in one day = B's work in a day + C's work in a day
= 1/15 + 1/15
= 2/15
So (B+C) can complete the work in 7 days and 1/2 days
Note:- You can see that efficiency of A, B & C are equal as they all take same days to complete the work alone.
I hope it will help you.