Math, asked by nandinisharma19, 10 months ago

pls help me to solve this question class 8 ch 13 time and work​

Attachments:

Answers

Answered by shivam018
2

Piece of work done by A, B, C in one hour= 1/8

Piece of work done by A in one hour= 1/15

Piece of work done by B in one hour= 1/20

Time taken by C to do the work =1/8-(1/15+1/20)

=1/8-7/60

=1/120

= 120 hours.

Hope I help you.