Math, asked by disha9047, 11 months ago

Pls pls pls pls pls pls pls pls help me

Attachments:

Answers

Answered by asifkhan13
0
a contract to complete a stadium in 9 months=560 persons
--------;----------_---------------=560×9
the contract complete the job in 5 months=960×9÷5
=1008 is extra person should he employ to complete the work


Answered by sprao534
0
I hope it helps you. See the attachment
Attachments:
Similar questions