Plz solve this math problem for me
Attachments:
Answers
Answered by
1
Answer:
16 days
Step-by-step explanation:
A+B=18 Days
in one day they do= 1/18 work
B+C DO A WORK IN 24 DAYS
IN ONE DAY THEY DO 1/24 WORK
A+C DO A WORK IN 36 DAYS
IN ONE DAY THEY DO 1/36 WORK
IN 2 DAYS. ABC CAN DO WORK= 1/18+1/24+1/36
=9/72
=1/8
IN 1 DAYS. ABC CAN DO WORK =1/16
1/16 WORK ABC CAN DO IN 1. DAY
WHOLE WORK ABC CAN DO IN 16 DAYS