Math, asked by 00252618690281, 9 months ago

Plz solve this math problem for me

Attachments:

Answers

Answered by sajalgupta2006
1

Answer:

16 days

Step-by-step explanation:

A+B=18 Days

in one day they do= 1/18 work

B+C DO A WORK IN 24 DAYS

IN ONE DAY THEY DO 1/24 WORK

A+C DO A WORK IN 36 DAYS

IN ONE DAY THEY DO 1/36 WORK

IN 2 DAYS. ABC CAN DO WORK= 1/18+1/24+1/36

=9/72

=1/8

IN 1 DAYS. ABC CAN DO WORK =1/16

1/16 WORK ABC CAN DO IN 1. DAY

WHOLE WORK ABC CAN DO IN 16 DAYS