plz solve this ques
Attachments:
Answers
Answered by
2
Answer:
Let a and b be the work that can be done per day by A & B respectively .
a = 1/8.
Therefore
(24/5) [ (1/8) + b] = 1
[ (1/8) + b] = 5/24
[ (3/24 + b] = 5/24
b = 2/24 = 1/12
B takes 12 days to complete the work.
Step-by-step explanation:
hope it helps
have a good day ahead!