Math, asked by Anonymous, 1 year ago

plzz define by language ...

Attachments:

Answers

Answered by ADITYA1100
1
A can do 2/3 of work in 16 days.
Therefore, A can do the whole work in (3/2* 16) = 24days.
B can do 1/4 of work in 3 days.
Therefore, B can do the whole work in (4*3) = 12 days.
Therefore, (A + B) 's 1 day's work = (1/12 + 1/24)
= 3/24 = 1/8.

Therefore, A and B together do the work in 8 days.

Hope that it will help you.