Plzzzzzz answer
12men working 6 hours per day can do a piece of work in 14 days. How many workers can complete the samr work in 8days working 7 hrs per day
Answers
When more than one man/machine work on a particular work or project, the rate of work is calculated as the strength of workers working in a particular time.
So amount of work = men*days*hours.
Since here work is constant,
M 1 X D 1 X H 1 = M 2 X D 2 X H 2
12 X 14 X 6 = M 2 X 8 X 7
M 2 = 18.
Hence 18 men can complete the same work iñ 8 days, working at 7 hours per day.
plz mark as brainliest
have a good day
Answer:
Step-by-step explanation:
Given,
12 men working 6 hr day work in 14 days
X men working 7 hr day work in 8 days
no of men is inversely proportional to the no of hours and also inversely proportional to no of days
12/x = 7 : 6 :: 8 : 14
12/x = 7 x 8 /6 x 14
12/x = 4/6
x= 12 x 6 /4
x= 3 x 6 = 18
Therefore 18 Men required to complete the work in 8 days working 7 hrs per day