Practice Set 38
1. Five workers take 12 days to weed a
field. How many days would 6 workers
take ? How many would 15 take ?
3. ME
lo
h
Answers
Answered by
0
Answer:
1st part
We have,
Worker W
1
=5
Weed a field in days=D
1
=12days
If,
Take worker W
2
=6
Then, Days D
2
=?
Then, we know that,
W
1
D
1
=W
2
D
2
5×12=6×D
2
D
2
=
6
5×12
D
2
=10days
2nd Part,
If workerW
3
=15
Then,
Days D
2
=?
Then, we know that,
W
1
D
1
=W
3
D
3
5×12=15×D
3
D
3
=
15
5×12
D
3
=4days
Hence, this is the answer.
Answered by
25
Step-by-step explanation:
5x × 12 = 60x
60x=6x × y
60x / 6x = y
10= y
y=10
60x = 15 × yx
y= 60x / 15x
y=4