30 machines = 60 days


The number of machines is inversely proportion to the number of days:

⇒ more days, less machine

⇒ more machines, less days


Find the number of machines needed if the job has to be completed in 1 day:

60 days = 30 machines

1 day = 60 x 30 = 1800 machines


Find the number of machines needed if the job has to be completed in 40 days:

1 day = 1800 machines

40 days = 1800 ÷ 40 = 45 machines


Answer: 45 machines are needed to complete the job in 40 days.