Pradeep receives an export order for garments. He has 30 machines to complete the order in 60 days. How many machines would be required to complete the job in 40 days?
Answers
Answered by
67
30 machines = 60 days
The number of machines is inversely proportion to the number of days:
⇒ more days, less machine
⇒ more machines, less days
Find the number of machines needed if the job has to be completed in 1 day:
60 days = 30 machines
1 day = 60 x 30 = 1800 machines
Find the number of machines needed if the job has to be completed in 40 days:
1 day = 1800 machines
40 days = 1800 ÷ 40 = 45 machines
Answer: 45 machines are needed to complete the job in 40 days.