Pradeep receives an export order for garments. He has 30 machines to complete the order in 60 days. How many machines would be required to complete the job in 40 days?
a. 50
b. 25
c. 35
d. 45
Answers
Answered by
2
He has 30 machine to complete the order in 60 days. so, 60*30=1800 and the machines would be required to complete the job in 40 days, 1800/40=45
Similar questions
History,
6 months ago
Math,
6 months ago
Chemistry,
6 months ago
Environmental Sciences,
1 year ago
Physics,
1 year ago