Math, asked by chiku7435, 1 year ago

Pradeep receives an export order for garments. He has 30 machines to complete the order in 60 days. How many machines would be required to complete the job in 40 days?

a. 50

b. 25

c. 35

d. 45

Answers

Answered by amansingh48
2

He has 30 machine to complete the order in 60 days. so, 60*30=1800 and the machines would be required to complete the job in 40 days, 1800/40=45