prepare a estimate of Manpower, Machinery
and Material resources required for the project
Answers
Answered by
0
Without knowing the skill mix you need and your daily working hours, you can calculate resource requirements as follows:
Schedule of the project = 20 days.
Cost of the project = 100 man days.
Standard working day = 7.5 hours.
Standard 5 day working week = 37.5 hours.