Prepare a preliminary estimate of four storeyed office building having total carpet
area of 2000sq.m for obtaining the administrative approval of the government, given
the following data. It may be assumed that 40% f the built up area will be taken up by
corridors, verandah, lavatories, staircase etc.
Plinth area rate in Rs. 4500/- per sq.m.
Extra due to deeper foundation at site 1 % of building cost.
Extra for special architectural treatment 0.5% of building cost.
Extra for water supply and sanitary installations at 8% of building cost.
Extra for internal electrical installation at 12.5% of building cost.
Extra for other services 5% of building cost.
Contingencies – 2.5%
Supervision charges – 10 %.
Answers
Answered by
7
Answer:
A particle has a displacement of 40m along OX in the first 5s and 30m perpendicular to OX in
the next 5s. The magnitude of average velocity of the particle during the time internal of 10s is
a) 6 ms–1 b) 7 ms–1 c) 8 ms–1 d) 5 ms–1 [
Similar questions
Art,
4 months ago
English,
4 months ago
Math,
4 months ago
Geography,
9 months ago
Math,
9 months ago
Social Sciences,
11 months ago
India Languages,
11 months ago
Geography,
11 months ago