prepare average due date
Attachments:
Answers
Answered by
9
Answer:
Average due date = 20-07-2016
Explanation:
Average due date =
Base date + [Total of product ÷ Total of amount]
04-07-2016 + [ 33,125 ÷ 2,075 ]
04-07-2016 + 15.96
i.e. Base date + 16 days
04-07-2016 + 16 = 20-07-2016
Average due date = 20-07-2016
-------------------------------------------------------------------
Calculation of days
From 04-07-2016 to 13-08-2016
- 31 + 9 = 40 days
From 04-07-2016 to 08-08-2016
- 31 + 4 = 35 days
From 04-07-2016 to 23-07-2016
- 19 days
From 04-07-2016 to 13-09-2016
- 31 + 31 + 9 = 71 days