Accountancy, asked by rajkumarjaiswal8967, 3 months ago

Progress payments in contracts
are based as a percentage of​

Answers

Answered by Anonymous
19

Question:-

Progress payments in contracts

are based as a percentage of

AnsWeR:-

Progress payments provide benefits to everyone up and down the payment chain. They allow owners and/or prime contractors to review the subcontractors' work before it's complete, and resolve disputes before the project is over.

Answered by Pratham2508
0

Answer:

Progress payments in contracts are based on a percentage of​ cost incurred by the contractor.

Explanation:

  • Progress payments are determined by incurred costs.
  • As the work under the contract is completed, payments are provided based on the costs incurred by the contractor.

When a request is submitted to the Contracting Officer and accepted, the contractor is normally paid between 7 and 30 days afterward:

  • Payments are determined by the degree or level of completion attained;
  • Government accepts payments for incomplete delivery;
  • Payments in part for a proposed contract termination; or
  • Payments depend on performance.

As was already mentioned, normal progress payments are calculated as a proportion of the contractor's costs. Although payments made under a cost-reimbursement contract are comparable to this procedure.

#SPJ2

Similar questions