Math, asked by rs6607576, 23 days ago

Puru alone can finish a work in 14 days and Krishna alone can finish can do it in 11 days How much time will they take to complete the work if they work together?

Answers

Answered by YennyPenny
0

Step-by-step explanation:

Let "60 units" represent the work done.

1) Find how many units Puru can do in 1 day.

  60 units / 14 days = 4.28571428571

  Puru can do 4.28571428571 units a day.

2) Find how many units Krisha can do in 1 day.

   60 units / 11 days = 5.45454545455

   Krisha can do 5.45454545455 units a day.

3) Find how many units Puru and Krisha can do together in 1 day.

   4.28571428571 + 5.45454545455 = 9.74025974026

    Together, Puru and Krisha can do 9.74025974026 units a day.

4) Find how many days will they finish the work together.

   60 units / 9.74025974026 units = 6.16

   Because we are dealing with days the answer should not have a remainder.

   

Answer:

Together, Puru and Krisha can complete the work in 6 days 9 minutes and 36 seconds.