Q.1 Praveen buys goods on credit on following dates. 10 days credit is allowed to him after which interest @ 8% p.a. is charged by supplier. 30th July 12,000 12th August 25,000
27th July 18,000
10th September 37,000
12th September 21,000
It was agreed to be settled on 30th September. Compute interest payable by using Average Due Date.
Answers
"Average Due Date is 23rd August and Interest is 941.15"
Explanation:
Average Due Date
Due Dates Amount No.of days from 27th July Product
27th July 18000 0 0
30th July 12000 3 36000
12th August 25000 15 375000
10th September 37000 44 1628000
12th September 21000 46 966000
Total Amount = 113000 3005000
and Product
Therefore, 27th July + 3005000/113000 =
27th July + 27 days = 23rd August
So,
Interest Payable = 23rd August to 30th September i.e 38 days
= 113000 x 8/100 x 38/365 = 941.15