Q.11 : A takes 2 hours more to do certain piece of
work than B. Also B does
1
th
40
work more
than A in one hour. How much time A takes
to complete the work alone?
(A) 10 hrs (B) 8 hrs
(C) 12 hrs (D) 5 hrs