Q.15 Planning results in
decreasing
O a) Coordination
b) Proper use of resources
O c) Future uncertainties
O d) Control
Answers
Answered by
11
Answer:
C.future uncertainties
Explanation:
· It reduces aimless activity and makes action more meaningful. (ii) Planning reduces the risk of uncertainty Planning is always done for future and future is uncertain. With the help of planning, possible changes in future are anticipated and various activities are planned in the best possible way.