Q.18 "A" can complete a certain work in 18 days and 'B' can do the same wor
in 15 days."B" worked for 10 days and left the job. In how many days ca
'A' alone finish the remaining work?
1) 5 days 2) 51/2 days 3) 6 days
4) 8 days
Answers
Answer:
hope it's helpful to you
Step-by-step explanation:
b worked for 10 days. So, remaining 5 days work is pending. This is 5/15 = 1/3rd of work. a can finish the work in 18 days.
Answer:
Option 3
Step-by-step explanation:
Given:-
A" can complete a certain work in 18 days and 'B' can do the same work in 15 days."B" worked for 10 days and left the job.
To find:-
In how many days can 'A' alone finish the remaining work?
Solution:-
Given that
Number of days that A can finish the work =
18 days
A can finish the work in 1 day = 1/18 th part of the work
Number of days the B can finish the same work =
15 days
B can finish the work in 1 day = 1/15th part of the work
Number of days B worked before left = 10 days
Total working part of B = 10×(1/15)
=> 10/15
=> 2/3
So remaining work will be
part of A + Part of B = 1
Part of A = 1- Part of B
Part of A = 1-(2/3)
=> (3-2)/3
=> 1/3
Remaining work = Part of A = 1/3
Number of days that A can finish the work alone
= Total working days of A× working part of A
= 18×(1/3)
=> (18/3)
=> 6 days
Answer:-
'A' alone can finish the remaining work in 6 days