Q.20 :-X and Y can
do a piece of work
in 20 days and 12
days respectively. X
started the work
alone and then
after 4 days Y
joined him until the
completion of the
work. How long did
the work last?
Answers
Answered by
0
Answer:
10 days
Step-by-step explanation:
Assume the work done to be 60 units which is the lcm of 20 and 12
so X completes the work in 20 days that means he does 3 units of work in one day(60/20=3)
and similarly Y completes the work in 12 days that means he does 5 units of work in one day(60/12=5)
now X starts the work and works alone for 4 days that means he completes 4*3=12 units of work in 4 days
now the remaining work is 60–12=48
now Y joins X so total units that can be completed in 1 day =3+5=8
now the remaining work can be completed by X and Y in 6 days that is 48/8=6
so total days required to complete the work is 4+6=10 days
so your answer will be 10 days
MARK ME BRAINLIST AND FOLLOW ME TO KNOW MORE ANSWER FOR UR QUESTIONS