Q.27 If 7 men working 6 hrs a day take 12 days to complete a task, then how many days wili 3 inen working 8 hrs a day time to do the same work?/ याद आदनी, 6 घंटे प्रतिदिन काम करने पर किसी काम को 12 दिन मे पूरा करते है तो 3 आदमी 8 घंटे प्रतिदिन काम करने पर कितने दिनों में उसी काम को पूरा कर लेंगे ​

Answers

Answered by vishalns1994
6

Answer:

3 men working for 8 hrs. a day will take 21 days to complete the work

Step-by-step explanation:

Given : Men M₁ = 7, Hours/day H₁ = 6, Days D₁ = 12

            Men M₂ = 3, Hours/day H₂ = 8. Days D₂ = ?

Solution : Since the work is same,

M₁ x H₁ x D₁ = M₂ x H₂ x D₂

∴ D₂ = M₁ x H₁ x D₁/ M₂ x H₂

       = 7 x 6 x 12/3 x 8

       = 21 days