Q.29 A contractor can complete a certain piece of work in 9 days. He employed certain number of men, but 6 of them being
absent from the very first day, the rest could finish the work in 15 days. How many men were originally
employed?
Answers
Answered by
10
Answer:
i hope you got answer
Step-by-step explanation:
Let there be x men at the begining less men, more days
∴ 15:9::x:(x−6) ⇒ 15(x−6)=9x
⇒ 6x=90 ⇒ x=15