Computer Science, asked by ankitkundlas3, 5 months ago

Q.3 of 16
Project evaluation should ideally be
conducted
(1 marks)
Choose the correct answer:
at the end of the project
after every system tuning
after the end of every stage of a project life
cycle and at the end of a project
after the deployment of the system​

Answers

Answered by knowledgecentre59
6

Answer:

Correct option: After the end of every stage of a project life cycle and at the end of a project

Explanation:

In my opinion, Project evaluation should ideally be

conducted at the end as well as after each stage of project life cycle.

Because in software industry, what matters the most is the quality of the software. And not how fast you have done the project. Even if you have completed the project in time or you have completed the project earlier evaluation is important at every stage of the project as well as at the end of the project, to maintain a better quality for the project.

Hope it helps.

Answered by hahjhelpline
1

after end of the project is th right ans

Similar questions