Q. 3. Study the following case/situation and express your opinion : (Any TWO) (6) (1) In Fine Diamonds Ltd, 200 employees are working in three shifts. In first shift 60 employees, in second shift 60 employees and in the third shift 80 employees are working without sufficient breaks except lunch break and shift change break. No employee is able to complete the work in designated time due to inappropriate time management which results into delay for next shift employees.
(i) Identify which scientific principle needs to be followed by the company.
(ii) Why the work is not completed in time?
(iii) Suggest the best solution to avoid such problem.
Answers
Answered by
0
Answer:
but i don't now the meaning of employees
Answered by
2
Answer:
Explanation:
1 In the above case, the Principle of scientific management called Science, Not Rule of Thumb needs to be followed
2 Work study base on Fatigue study and Scientific task setting can be used for smooth flow of work in ‘Fine Diamonds Ltd.
3 Following are the reasons for non-completion of work on time are:
a) Long working hours without sufficient breaks reduce the efficiency of labour.
b) Due to inappropriate time management which results in delays for the next shift employees.
c) Standard required output and standard time are not defined by Management of the Fine Dimond Ltd.