Q-4. Information on the activities required for a project is as follows:
Name OF THE ACTIVITY
NODE
DURATION (days)
A
1-2
2
B
1-3
7
C
1-4
8
D
2-5
3
E
3-5
6
F
3-6
10
G
3-7
4
H
4-6
6
I
5-7
2
J
6-8
5
K
7-8
6
Draw the network Diagram
Determine the critical path and show it on the network diagram
Answers
Answered by
0
Answer:
draw the network diagram
Answered by
2
Answer:
A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node 10 is __________