Business Studies, asked by mandlois98, 2 months ago


Q-4. Information on the activities required for a project is as follows:
Name OF THE ACTIVITY
NODE
DURATION (days)

A
1-2
2

B
1-3
7

C
1-4
8

D
2-5
3

E
3-5
6

F
3-6
10

G
3-7
4

H
4-6
6

I
5-7
2

J
6-8
5

K
7-8
6








Draw the network Diagram
Determine the critical path and show it on the network diagram​

Answers

Answered by siddhantvarma3
0

Answer:

draw the network diagram

Answered by veerajagarwal
2

Answer:

A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node 10 is __________

Similar questions