Math, asked by patilsurekha1969, 11 months ago

Q. 42: A completes certain work in 20 days. B can do th of
same work in 3 days, C is twice efficient than B. If they work
together, then in how many days they will complete the work?
A) 10 B) 15 097 D) 10-
i​

Answers

Answered by MavisRee
0

Answer:

Work is completed in 0.95 days if A, B and C work together

Step-by-step explanation:

A can complete work in 20 days

B can complete work in 3 days

Also, C is twice efficient than B

Thus, C complete work in \frac{3}{2} days

A's one day work =\frac{1}{20}

B's one day work =\frac{1}{3}

C's one day work =\frac{2}{3}

Total work is LCM of (20, 3 and 3) =60\hspace{0.1cm}parts

A's one day work =3\hspace{0.1cm}parts

B's one day work =20\hspace{0.1cm}parts

C's one day work =40\hspace{0.1cm}parts

(A + B + C)'s 1 day work =63\hspace{0.1cm}parts

63 parts of work takes 1 day

60 parts of work takes  \frac{60}{63} = 0.95 days