Q 55 Paul and Peter undertake to do a piece
of work for $500. Paul alone can do a
work in 5 days, Lisa alone can do it in 10
days. If Peter helps them they can finish
the work in 3 days. What will be the
approximate share of Peter?
Answers
Given :
Paul and Peter undertake to do a piece of work for $500
Paul alone can do a work in 5 days
Lisa alone can do it in 10 days.
With the help of Peter they can finish the work in 3 days
To Find :
The approximate share amount of Peter
Solution :
Paul alone can do a work in 5 days
So, Paul 1 day work =
With the help of Peter they can finish the work in 3 days
∴ Paul 3 days work =
Lisa alone can do it in 10 days
So, Lisa 1 day work =
∵ With the help of Peter they can finish the work in 3 days
∴ Lisa 3 days work =
Let Peter alone can complete work in x days
So, Peter 3 days work = 1 - ( Paul 3 days work + Lisa 3 days work )
= 1 - ( + )
= 1 - ( )
= 1 -
=
=
Again
The ratio of their share = : :
i.e = 6 : 3 : 1
Now, Peter's share = × $ 500
= × $ 500
∴ Peter's share = $ 50