Q - 6. 2 persons could fit doors in a house in 3 days . How many persons would be needed to dit doors in 1 day ?
a) 3 persons
b) 6 persons
c) 4 persons
Answers
Answered by
0
Answer:
6 person can fit the windows in one day
Answered by
0
Answer:
6 persons is needed to fit