Q.6 The standard time taken to complete a product is 12 hours at 25 p. per hour.
Time wages are allowed to workers taking more than the time allowed but workers
who complete the job in standard time or less receive a straight piece work rate
plus 10%bonus i.e. 12 hours at Rs. 0.275. calculate the wages carned by A.B.C and
D who complete the job in 15,12,10,8 hours respectively. What will be their
effectively hour rate?
Answers
Answered by
0
Explanation:
The standard time taken to complete a product is 12 hours at 25 p. per hour. Time wages are allowed to workers taking more than the time allowed but workers. who complete the job in standard time or less receive a straight piece work rate. plus 10%bonus i.e. 12 hours at Rs. 0.275.