Math, asked by khageshbansal, 1 month ago

Q.62 Weaver 'A' can weave a saree in 60 days. He weaves it for 20 days and then weaver B' alone finishes the remaining work in 30 days in how many days will weavers 'A' and B' working together finish the work?

options
1. 22 5/6
2.25 5/7
3. 25 5/6
4. 22 5/7


according to book correct answer is 22 5/6. how?​

Answers

Answered by mahima930
1

Answer:

yess option 1 is correct...

Answered by ktasmiyasultana07
1

Answer:

Step-by-step explanation:

yes it is correct