Q. A, B & C can do a piece of work in 12, 20, & 30 days respectively. If A is assisted everyday alternately by B & C in how many days was the work completed? A. 6 days B. 8 days C. 7 days D. 3 days
Answers
Answer:
LCM (12,20,30)= 180 units
units per day A 180/12= 15
B 180/20= 9
C 180/30= 6
A,B,C can do work 15+9+6 =30 units per day
A is alternative working
1st day working A,B,C = 30units
2nd day A not working B,C work = 9+6 =15 units
in 2days 30+15 =45units
=2/45 *180= 8
Answer:
Concept:
Least common multiple (LCM) is a method to find the least common multiple between any two or more numbers. A common multiple is a number that is a multiple of two or more number.
LCM is also used to add or subtract any two fractions if the denominators of the fractions are different. When performing any arithmetic operations such as addition, subtraction with fractions, LCM is used for the common denominator. This process simplifies the simplification process.
Find:
We find that how many days was the work completed
Given:
A, B & C can do a piece of work in 12, 20, & 30 days respectively.
Step-by-step explanation:
Let the total work be 220 units (LCM of 11, 20 & 55)
= 20 unit per day
= 11 units/day
= 4 untis /day
according to the question,
(20+11) +(20 +4)+(20+11) + (20 +4)+.
(A+B) + (A + C) + (A + B) + (A + C) +.....
In 2 days, work get completed = 55 units.
55 units of work completed in 2 days.
220 units of work completed in
= 2 x 4
= 8days
#SPJ2