Q. A, B & C together can do a work in a 4 days, A alone can do the work in 12 days & B alone can do the same work in 18 days. Find in what time C alone can do that work?
Answers
Answered by
8
Answer:
C alone completes the work in 9 days .
Step-by-step explanation:
In 4 days,
A & B together do
4*(1/12 + 1/18) = 5/9 of the work .
... Hence, C alone completes the work in 9 days .
Thank you!!!