Answer:

please mark me as brainest

Step-by-step explanation:

B will require 10 days to complete the whole work alone.

A does 7/10th of the work in 14 days.

So he will require 20 days to complete the whole work.

After 14 days 3/10th of the work is remaining.

Of this when they work together A does 1/20x2 or 1/10 th of the work and the balance 2/10 of the work is done by B.

To do 1/5th of the work B requires 2 days.

To do the whole work he will require 10 days.