Q Dikshit and Sammit can do a work in 36 days and 24 days respectively. They started the work together but
Sammit left after 3 days before the completion of the work. How much time will be taken to complete the
work?
Ops: A. 13.2 days
B. 17.4 days
C. 11.33 days
D. 16.2 days
Answers
Answer:
dikshit - a , sammit- b
Step-by-step explanation:
The required equation is
27/36 + (27- N)/24= 1
So 3/4 + 27/24- N/24= 1
SoN/24= 27/24+ 3/4- 1 = 21/24
So N= 21.
Therefore A- joined -B after 21- days to complete the work.
=============================
Another Method:
In 27- days -B- alone will complete 27/36= 3/4- part of the work.
So the remaining (1–3/4)= 1/4- part of the work was exclusively done by A- alone. He will complete 1/4 of the work in = (1/4)/1/24)= 6- days.
He worked only for 6- days. ie he joined B- after (27- 6)= 21- days.
OK.
+++++++++++++++++++++++++++++
After 21 days, A joined.
Assign X to the number of days B worked alone. Assign total work value as Unit 1.
Output of A per day= 1/24 unit; output of B per day=1/36 unit; work done by B alone = x days*1/36 unit work/day…=X/36 unit. Work remaining = 1-(x/36).
work done by A and B together= (27-X)*(1/24)+ (27-x) *1/36={1-(x/36)}.
solve for x, u get X=21.
Efficiency of A = 1/24 th part of work per day
Efficiency of B = 1/36 th part of work per day
A joined B say after n days
Part of work done by B in n days = n/36 th
The work remained to be done = (1 - n/36)
The combined efficiency of A & B = 1/24 + 1/36 = 5/72 th part of work per day
(1 - n/36)*72/5 = 27 - n
72 - 2n = 135 - 5n
3n = 135 - 72 = 63
n = 21
A joins B after 21 days
please mark my answer as brainliest .