Q no . 6 men can complete a piece of work in
20 days. In how many days will 8 men
complete the same piece of work?
(a) 12 days
(b) 14 days
(c) 15 days
(d) 16 days

Answers

Answered by shivajikaithi
2

Answer:

in 16 Days ...................

Answered by Ayushman2007Ayushman
0

Answer:

(c) 15 days

Step-by-step explanation:

8:6::20:x

x= (6X20)/8 = 15