Q:Sudhir and Shyam can do a work in 12 days, while Shyam alone can complete it in 30 days. In how many days can Sudhir complete that work alone?​

Answers

Answered by jasmeetkaurji2000
0

Step-by-step explanation:

Ram takes 20 days to complete a piece of work.

Shyam takes 30 days to complete a piece of work.

Ram completes (1/20) of a piece of work in 1 day.

Shyam completes (1/30) of a piece of work in 1 day.

Together R and S complete (1/20) + (1/30) = (1/12) of a piece of work in 1 day.

(1/12) of a piece of work - 1 day

(12/12) of a piece of work - (12/12)/(1/12) = 12 days.

R and S take 12 days to complete a piece of work when they work together.