Q2. If 4 men can complete a work in a week, how many will complete the same work in two
weeks?
Answers
Answered by
1
Answer:
2
Step-by-step explanation:
W1 * T1 = W2 * T2
W1 = 4 men
T1 = 1 week
T2 = 2 weeks
ie, 4*1 = W2 * 2
so, W2 = 2 men