Q3:12workers can build a wall in 50hrs how many workers will be required to do same work in 40hrs *
Very important please tell fast
Answers
Answered by
1
Answer:
15
Step-by-step explanation:
workers. hours
12. 50
x. 40
12 × 50 = x 40
40 is go to another side it's change into division
12 × 50 ÷ 40 = x
600 ÷ 40 = x
(x = 15)
answer = 15 workers in 40 hours
(15:40)