Q4.If 16 men working 7 hours a day can paint a building in 48 days then how many days will 14 men take working 12 hours a day to paint the same building?
Answers
Answered by
1
Answer:
56
Step-by-step explanation:
days. men
48. 16
? 14
cross multiply
?=14×48/16
?=14×4
?=56