Q4.If 16 men working 7 hours a day
can paint a building in 48 days then
how many days will 14 men take
working 12 hours a day to paint the
same building?
Answers
Answered by
2
Answer:
8 men working for 9 hours a day can complete a piece of work in 20 days
8 men working for 1 hour a day can complete the work in (20 x 9) days (Less hours, More days)
1 man working for 1 hour a day can complete the work in (20 x 9 x 8) days (Less men, more days)
1 man working for 10 hours a day can complete the work in (
10
20×9×8
) days
7 men working for 10 hours a day can complete the work in (
7×10
20×9×8
) days =
7
144
days = 20
7
4
days