Q7. A and b can do a piece of work in 30 days, while b and c can do the same work in 24 days and c and a in 20 days. They all work together for 10 days when b and c leave. How many days more will a take to finish the work?

Answers

Answered by harrypotter863
2

total work =( A + B )+( B+C)+(C +A)

= 2(A+B+C)work

= 2× (1/30 +1/24+1/20)

in this way time taken by A will be 11.5 days