Q8. The free float is equal to
Answers
Answer:
Free float is measured by subtracting the early finish (EF) of the activity from the early start (ES) of the successor activity. Free float represents the amount of time that a schedule activity can be delayed without delaying the early start date of any immediate successor activity within the network path.
Explanation:
Answer:
Free float is measured by subtracting the early finish (EF) of the activity from the early start (ES) of the successor activity. Free float represents the amount of time that a schedule activity can be delayed without delaying the early start date of any immediate successor activity within the network path.
Explanation:
Free float is measured by subtracting the early finish (EF) of the activity from the early start (ES) of the successor activity.
Free float is only calculated on the last activity in an activity sequence.
Example
If activity 1.4 has a duration of 6 days and is occurring concurrently with activity 1.5 which has a duration of 9 days, activity 1.4 has 3 days of total float. Meaning, it can be delayed up to three days without any effect on the project.
However, if activity 1.4 is delayed by 5 days, there is now a negative float situation: -2 days. This reflects the fact that the project will now take two days longer than anticipated.