Question 13
2
Rocket propulsion company is considering the expansion of a
solid propellant manufacturing process by adding more 1-ton-
capacity curing furnaces. Each batch (1 ton) of propellant must
undergo 30 minutes of furnace time; including load and upload
operations. However, the furnace is used only 80% of time due to
power restrictions in other parts of the system. The required
output for the new layout is to be 16tons per shift (8hours). Plant
(system) efficiency is estimated at 50% of system capacity.
Determine the number of furnaces required.
Answers
Answer:
See the answer
Eric Explosives Company is considering the expansion of a solid-propellant manufacturing process by adding more 1-ton capacity curing furnaces. Each batch (1 ton) of propellant must undergo 30 minutes of furnace time, including load and unload operations. However the furnace is used only 80 percent of the time due to power restrictions in the other parts of the system. The required output for the new layout is to be 16 tons per shift (8 hours). Plant (system) efficiency is estimated at 50 percent of system capacity. Determine the number of furnaces required. Refer to problem no. 4, estimate the percentage of time the furnaces will be idled.
Show transcribed image text
Expert Answer
100% (1 rating)
Required output = 16 tans per shift(8 hours) 8hrs = 8 times 60 = 480 min purchaces use only 80% of time total time for use of turnace in = 480 times 80/100 =
view the full answer
Previous question
Next question
Transcribed Image Text from this Question
Eric Explosives Company is considering the expansion of a solid-propellant manufacturing process by adding more 1-ton capacity curing furnaces. Each batch (1 ton) of propellant must undergo 30 minutes of furnace time, including load and unload operations. However the furnace is used only 80 percent of the time due to power restrictions in the other parts of the system. The required output for the new layout is to be 16 tons per shift (8 hours). Plant (system) efficiency is estimated at 50 percent of system capacity. Determine the number of furnaces required. Refer to problem no. 4, estimate the percentage of time the furnaces will be idled.