Question # 14
GRev
One man works for 10 hrs/day for 3 days to nnish a work Aboy finishes the same in 5 days won
18 hrs/day. How many boys are required to do the job in the time taken by 1 man?
Answers
Answered by
1
1 boy takes 90hrs to do the work whereas a man takes on 30hrs
So, boys required = 90/30
= 3
Therefore, 3 boys are required.