Question 17
Question
2) If 2 men works together then they can do the work in 12 hours. If 1 men
do the work 10 hours faster than the other. How many hours does it take
the second man to do the work?
Note: enter only the number as answer.
O Type here to search
O
DI
Answers
1 man= 10 hr
2 man=20-12=8 hr
Given:
2 men work together then they can do the work in 12 hours.
If 1 man do the work 10 hours faster than the other
To find:
How many hours does it take the second man to do the work
Solution:
Let
number of hours taken by A to complete the work = x hours
Amount of work done by A in 1 hour = 1/x
number of hours taken by B to complete the work = y hours
Amount of work done by B in 1 hour = 1/y
Given that
A does the work 10 hours faster than the other
x = y + 10 (1)
A and B can do the work together in 12 hours. Therefore, in one hour they will do 1/12th of the work.
(2)
Now, we will solve these two equations to find the values of x and y.
Putting the value of x from (1) into (2) we get an equation
=
we will use splitting the middle term method to find the factors
=
=
From this, we will get y = -6, 20
we will take the positive value. Therefore, y = 20
The second man will take 20 hours to complete the work.