Math, asked by Theking0123, 7 days ago

Question :-

19 boys can do a piece of work in 25 days. In how many days can 28 boys do the same work ?​

Answers

Answered by Anonymous
6

Question :-

19 boys can do a piece of work in 25 days. In how many days can 28 boys do the same work ?​

Answer:-

Since 19 boys can do a piece of work in 25 days.

∴ 1 boy can do the work in = ( 19 × 25 ) days.

∴ 28 boys can do this =  ( 19 × 25 )

                                             28

= 17 days [ 16.96 days. On converting we get 17 ]

So 28 boys can do this work in 17 days ..

Hope this answer can helps u dear !! ✨♥