Question 24
8 men and 12 boys can nish a piece of work in 10 days, while 6 men and 8 boys can finish it in
14 days Find the time taken by one man alone and that by one boy alone to finish the work
Answers
Answered by
1
Answer:
280/3 Daya
Step-by-step explanation:
As we know that work =man ×days×hours
Here only person are changing but our work is constant.So depending upon available man and boy for work ,time will be change to finish it.